Long Description - Elevate Timeline

This image is a timeline that spans from January 2021 to August 2023. It depicts five phases of the Elevate Project. The first phase, "Plan," spans from January 2021 to April 2021. The second phase, "Architect," spans from May 2021 to October 2021. The third phase, "Configure and Prototype," spans from November 2021 to July 2022. The fourth phase, "Test and Train," spans from August 2022 to April 2023. The fifth and final phase, "Deploy," spans from May 2023 to July 2023. There is an illustration of a rocket under July that is meant to depict the launch or completion of the project.